Panel

In Zephyr Enterprise, releases consists of requirements that exist within the system for testing. Users can edit requirements to in the system which includes the following fields and options: PriorityAttachments, Mapped Test Cases, and a Description. To learn how to edit requirements, please view the steps below.

Terminology

Expand
titleClick to view more information on terminology regarding this page


TermDescription
RequirementsA single documented physical or functional need that pertains to a particular design, software, or product.
AttachmentsA file that can be attached to a requirement to help define/describe the requirement. (images, docs, etc.)
MappingLinking a requirement to an existing test case to build traceability between a requirement and test case.
DescriptionA body of text that helps to describe any additional details regarding the requirement that can't fit in the requirement title.








Column

Table of Contents

Panel
The steps below describe in detail the general process of adding, editing, cloning, deleting, deallocating and allocating, and importing and exporting requirements in a project for Zephyr Enterprise. To view further instructions for each individual function, please click the links provided below. By clicking on a link, you will be redirected to the page with the steps corresponding to the function selected. 

Child pages (Children Display)
alltrue
pageRequirements



Editing Requirements

Info
titlePrior to Editing a Requirement

Prior to editing a requirement, there must be an existing project, release, and requirement that has been created in Zephyr Enterprise. The project/release/ must be selected and the user must be under the Requirements section within the release selected. 

Scenario: You are a testing manager in Zephyr Enterprise. As a testing manager, you want to edit an existing requirement in Release 1.0 in project Mercury.

If this is your first time managing requirements, you might want to work within a test project rather than an actual project in the system, and that way, you can work out any issues you might have with managing requirements before you work with live requirements.


1. Simply click on the individual requirement that you want to edit in the table.

2. You can change any of the fields once you click on the existing requirement.

  • Feel free to change the name of the requirement, the description, the priority level, add any attachments or change the mapping of the test cases.
Info
titleNote

Once you edit or change a field, Zephyr Enterprise will automatically save your change.


3. After changing/editing any of the fields, click on the "Save" Button to finalize any changes. 